Description
ACCOMPLISHMENTS * Procured 18 projects worth $1,4 billion through the delivery of numerous professional presentations. * Recovered $1.5M in general condition and costs when client's issuance of change orders caused a 12- month delay on a $320M project. * Negotiated $44.5M in change orders and change directives on behalf of the employer with the resulting profit ranging from 12-20%. * Maintained a consistent buy-out rate of 9-15% on trades by reviewing/negotiating contracts.
Work Experience
COMPANY | POSITION HELD | DATES WORKED |
---|---|---|
Nationwide | Vice President Of Operations | 1/2011 - 1/2017 |
Leon D. De Matteis Corp. | Project Executive | 1/2007 - 1/2011 |
Vcg Construction | Vice President / Project Executive | 1/2005 - 1/2007 |
Bovis Lend Lease | Senior Project Manager | 1/2000 - 1/2005 |
(Confidential) | President Managing Director | 1/1994 - Present |